Motorwind LT ONE Solution
 
   
 
   
 
   
 
   
 
   
   
   
   
Quotation 1 Wind turbines only
item unit cost total cost
One sign board set with 25 turbines/5 generators 20 000 HK$ 100 000 HK$
one set of electrical equipment electrical box /regulators/batteries/change over (two sides) 13 000 HK$ 65 000 HK$
Copyrights & design and engineering 20 000 HK$ 20 000 HK$
Transportation 10 000 HK$ 10 000 HK$
1 working prototype 45 000 HK$ 45 000 HK$
AC consultant /structural engineer NA
Total 240 000 HK$
payment 100% in advance, upon order confirmation
 
   
Quotation 2 Wind turbines +PV panels
item unit cost total cost
One sign board set with 25 turbines/5 generators 20 000 HK$ 100 000 HK$
one set of electrical equipment electrical box /regulators/batteries/change over (two sides) 15 000 HK$ 75 000 HK$
8 PV panels 250x 230mm 6Watts each 7 500 HK$ 37 500 HK$
Copyrights & design and engineering 20 000 HK$ 20 000 HK$
Transportation 10 000 HK$ 10 000 HK$
1 working prototype (without PV panels) 45 000 HK$ 45 000 HK$
AC consultant /structural engineer NA
Total 287 500 HK$
payment 100% at the contract signature
 
   

The system will be delivered as ready-to-use item. There will not be any installation for Motorwind but a MOTORWIND engineer will monitor the installation at site.

 

schedule estimation:

Manufacturing : 4 weeks

Electrical cabling: 1 week

Installation: 3 days

Maintenance will be carried out By Motorwind authorized personnel only. A fee of HK$5 000 will be charged upon each visit.

Maintenance can only be carried out by using the building gondola, which will be provided by customer/building management.

The system is guaranteed for one year for parts and system.

Motorwind Ltd/ Motorwave Group keep all rights on Carbon Credit.

The primary purpose of these sign board is for advertizing, but due to the specific use and limited application

Motorwind Ltd will not charge any advertising fees.

 

Load and Weight and Forces

A) Signage Per Unit (total 5 units):

Weight without any fiber glass cover : approx 50 kgs :includes frame/turbines/electrical components.

B) Wall mounting frame:

Each: approx 10kgs

C) Pressure/wall concrete screws: we take approx 70Kg/m (700Nm)

so each of the 4 top screw head will take approx 15 to 20 kgs(150 to 200 N).

a 12 mm concrete screw head can take 10 000 N in pull out pressure and approx 40 000 N in

vertical loading so it is safe.

Lateral pressure for high wind speed.

For all of our installations, we use a flexible mounting frame that can allow absorbtion of high wind energy.

For this signage, we can only use a regid frame for security reasons.

A turbine under 50ms wind speed takes approx 12N

(We consider approx 5% of a solid wall).

For 25 turbines:300N.

We consider approx 300N/2m or 600N/m

So it is also very safe.

By adding a surface (with 30% solid wall) the board will take more pressure.

the effect is increased by having a cup effect.

We can consider(regarding areas involved total area =2.1 M2 :turbines = 1.6 M2)

that the whole board is max approx 10% to 15% of a solid wall.

 
   
   
 
Home I Team I Products I Installer Training I Facts & Media I Contact Us I Shopping

Motorwave Ltd. Copyright 2006